Project Data
End User: Capitol Lighting Paramus
Installer: Forest Electric Corp
Location: Paramus, NJ
Date of Install: Sept 2006 – Nov 2006
Size of System in kW: 140
Project Developer: American Energy Technology
Special Challenges Met: Very aggressive schedule.
Complete Project Team: Electrical Engineer: Engineered Design Group
Architect: Todd Koenig Structural Engineer: Thor
Project Brief:
Capitol Lighting is a retail specialty lighting showroom. Capitol Lighting consumes a large amount of energy when displaying lights to customers. TurtleEnergy designed a Photovoltaic system to be installed at Capitol Lighting by Forest Electric (Union Contractor.
Analysis:
TurtleEnergy undertook a detailed analysis of the site. This analysis was comprised of the following steps and implementation.
Shading Analysis
Optimal System Design and Concept Planning
Industrial Design of the Components of the System
Multi-Disciplinary Coordination with Architects, Structural Engineers, Electrical Engineers, and Construction Managers (Stellar Energy Solutions)
The project commenced in and was successfully completed
Project Data
End User: Capitol Lighting Paramus
Installer: Forest Electric Corp
Location: Paramus, NJ
Date of Install: Sept 2006 – Nov 2006
Size of System in kW: 140
Project Developer: American Energy Technology
Special Challenges Met: Very aggressive schedule.
Complete Project Team: Electrical Engineer: Engineered Design Group
Architect: Todd Koenig Structural Engineer: Thor
Project Brief:
Capitol Lighting is a retail specialty lighting showroom. Capitol Lighting consumes a large amount of energy when displaying lights to customers. TurtleEnergy designed a Photovoltaic system to be installed at Capitol Lighting by Forest Electric (Union Contractor.
Analysis:
TurtleEnergy undertook a detailed analysis of the site. This analysis was comprised of the following steps and implementation.
Shading Analysis
Optimal System Design and Concept Planning
Industrial Design of the Components of the System
Multi-Disciplinary Coordination with Architects, Structural Engineers, Electrical Engineers, and Construction Managers (Stellar Energy Solutions)
The project commenced in and was successfully completed